register |  login
Loading Ad
ADVERTISEMENT
Loading Tower

New flyover in Adams County marks major milestone
Contributed by: Joseph Kirchmer/YourHub.com on 7/24/2008

A new bridge scheduled to open next month should make it easier for Adams County residents to traverse the highways.

The 2,220-foot flyover ramp, which is in its final stages, will take motorists from eastbound Interstate 270 to eastbound Interstate 76. Currently, the only way for motorists to access eastbound I-76 from I-270 is via southbound I-25.

The project, coming in at a cost of $14.7 million, is considered a major milestone for the Colorado Department of Transportation (CDOT). It's the last of 10 major projects designed to improve the I-25/U.S. 36/I-270/I-76 interchange.

"Definitely, it's a huge milestone for us," said Mindy Crane, spokeswoman for CDOT. "This was a huge project and it will certainly make a huge difference."

The first of the 10 projects, which kicked off in June 1996, constructed a total of five bridges - two for westbound I-270 over Washington Street and I-25, two for the exit ramp from northbound I-25 to 70th Avenue and one for northbound I-25 to westbound U.S. 36.

Twelve years and approximately $110 million later, the project is nearly finished. Officials say the new flyover will make an immediate impact on an area that sees approximately 75,000 motorists on a daily basis.

Crews placed I-270 and I-76 into its final configuration July 24. The area had been temporarily realigned to the north to allow for construction of the bridge.

The flyover, which will be a one way road, still needs to be painted and equipped with anti-icing materials before it opens, according to officials. The entire project will be completed this November - crews still need to replace a loop from southbound I-25 to eastbound I-76.

A Look At The Ten Major Projects To Improve The I-25/U.S. 36/I-270/I-76 Interchange

Project 1
Cost: $12 million
Contractor: Centric-Jones Co.
Work: Constructed a total of five new bridges. Two of the bridges were for westbound I-270 over Washington Street and over I-25. Two bridges were for the exit ramp from northbound I-25 to 70th Avenue. The final bridge connected northbound I-25 to westbound US 36.
Duration: June 1996 through May 1998

Project 2
Cost: $9 million
Contractor: SEMA Construction Co., Inc.
Work: Constructed the I-270 westbound bridge over Clear Creek, widened the existing US 36 bridge over Broadway, realigned southbound I-25 to the westbound US 36 ramp, which included the construction of mechanically stabilized earth walls.
Duration: July 1997 through December 1998

Project 3
Cost: $19 million
Contractor: Centric-Jones Co.
Work: Completed the westbound I-270 extension between I-76 and US 36, built the Direct Connect HOV ramp between US 36 and I-25 and constructed a new alignment of northbound I-25 between I-76 and 84th Avenue.
Duration: June 1998 through June 2001

Project 4
Cost: $17 million
Contractor: Lawrence Construction Co.
Work: Reconstructed the US 36/Pecos Street interchange, reconstructed US 36 between Zuni Street and Lipan Street in concrete and built a sound wall.
Duration: January 1999 through June 2001

Project 5
Cost: $19.5 million
Contractor: Asphalt Specialties Co, Inc.
Work: Reconstructed the US 36/Federal Boulevard interchange, reconstructed US 36 to include HOV lanes between Lowell Boulevard and Zuni Street.
Duration: October 1999 through March 2002
I-270 Extension Projects

Project 6
Cost: $11.3 million
Contractor: Centric-Jones Co.
Work: Constructed the long eastbound structure over I-25, installed retaining walls on eastbound US 36 at Broadway, on the ramp from eastbound US 36 to southbound I-25 and on the ramp from eastbound US 36 to northbound I-25.
Duration: January 1993 through October 1994

Project 7
Cost: $21 million
Contractor: Hamon Contractors, Inc.
Work: Constructed seven structures at the I-270 and I-76 interchange, rebuilt ramp movements from westbound I-270 to eastbound and westbound I-76. This project was accelerated two years due to TRANs bonds.
Duration: June 2000 through August 2003

Project 8
Cost: $8.5 million
Contractor: Hamon Contractors, Inc.
Work: Constructed eastbound I-270 from I-25 to York Street, including the new bridge structures at I-270 over Washington Street and I-270 over Clear Creek. This project was accelerated one year due to TRANs bonds.
Duration: October 1999 through March 2002

Project 9
Cost: $21 million
Contractor: SEMA Construction Co., Inc.
Work: Constructed a flyover ramp from southbound I-25 to eastbound I-270 and reconstructed southbound I-25 in concrete between 84th Avenue and I-76. This project would not have been constructed without TRANs bond monies.
Duration: March 2004 through November 2005

Project 10
Cost: $18.7 million
Contractor: Edward Kraemer & Sons, Inc.
Work: Constructs a 2,200-foot flyover ramp from eastbound I-270 to eastbound I-76. The flyover opens in August with the rest of the project wrapping up in November.
Duration: December 2006 through November 2008

SOURCE: CDOT





SUBMIT COMMENT

Rate the above story



Talk Back : submit comments to the story

*Note: you need to log-in to add a comment or rating.

SAVE AND SHARE THIS STORY
STORY RSS FEEDS
WANT TO WRITE FOR YOURHUB.COM?
Want to see the stories you write and the photos you shoot featured in the YourHub.com Thursday print section available all over the Front Range and with home subscriptions of the Rocky Mountain News and The Denver Post? All you have to do is register, then post a story or column, start a blog or tell everyone what events are happening in town. We will print the best stories, columns, event listings, photos and blog entries in our print sections.

ADVERTISEMENT
Loading Ad

Loading Ad
ADVERTISEMENT
Loading Ad