Construction update: Indiana Street project


Bridge construction on Indiana Street over Croke Canal has been completed except for some minor punch list items. Indiana Street between West 52 nd Avenue and West 58 th Avenue is now open to through traffic.

The general contractor, KECI Colorado, Inc., completed the project approximately two months ahead of schedule. The newly constructed bridge was designed to be much safer for pedestrians, bicyclists, equestrian riders and motorists. The traffic lanes are twelve feet in width, and there are now four foot wide paved shoulders on each side of the bridge.

In addition, there is new curb, gutter, and sidewalk as well as new guardrails and bridge rail. Jefferson County Division of Highways and Transportation would like to thank the area residents and businesses and the traveling public for their patience during construction of the new bridge.

Guidelines: Be kind. Abusive commentary may be removed. If you believe someone has been abusive, please click "Report Abuse".

SUBMIT COMMENT
Talk Back : submit comments to the story

*Note: you need to log-in to add a comment or rating.
Thank you! Your comment has been updated.