e-mail:
password:
register
|
login
› NORTHGLENN
SEARCH YOUR HUB:
GO
advanced search
Loading Ad
STORIES
EVENTS
BLOGS
FOR SALE
YELLOW PAGES
PHOTOS
Local Info ›
Home ›
Help ›
Visit Other Hubs:
YourHub.com
Arvada
Aurora
Boulder
Brighton
Broomfield
Castle Pines
Castle Rock
Centennial
Cherry Hills Village
Commerce City
Conifer
Denver
Denver North
Denver South
Edgewater
Englewood
Erie
Evergreen
Federal Heights
Franktown
Glendale
Golden
Green Valley Ranch
Greenwood Village
Highlands Ranch
Lafayette
Lakewood
Littleton
Lone Tree
Longmont
Louisville and Superior
Montbello
Morrison
nights
Niwot
Northglenn
Parker
Roxborough
Sheridan
Thornton
TriTowns
Westminster
Wheat Ridge
ADVERTISEMENT
Loading Tower
RECENT STORIES
We are educated voters
(
DR. SEAN REIF D.C.
)
Residents falling for internet fraud
(
City of Northglenn Public Communications
)
Divorce: Poor financial choices impact family
(
Rosanne Gain
)
Men or machine
(
DR. SEAN REIF D.C.
)
Don’t miss winter fun on the ice
(
Robin Ginalick
)
share a story
|
more postings
»
YourHub.com
\\
Northglenn
\\
Stories
\\
News
\\
Traffic
SB I-25 ramp to WB US 36 to close Oct. 23 and 24
e-mail to a friend
|
print this
|
link to this
Contributed by:
CDOT
on 10/21/2005
DENVER -
On Oct. 23 and 24, the Colorado Department of Transportation (CDOT) will close the southbound I-25 ramp to westbound US 36 from 11 p.m. to 5:30 a.m. in order to place the ramp into its final configuration and remove the asphalt on the old ramp.
"Over the last several months, this ramp has been in a detour configuration so that the concrete reconstruction of southbound I-25 could take place," said CDOT Project Engineer Jim Powers. "Now that the reconstruction is complete in that area, we can move the ramp into its final configuration and then remove the remaining asphalt on the temporary ramp."
During the closure, southbound I-25 motorists needing access to westbound US 36 will have to take I-25 to 58th Avenue. Motorists will then take a left onto 58th Avenue and a left onto northbound I-25 where access to westbound US 36 is available.
In addition, on Tuesday night, starting at 9 p.m., a single right lane of southbound I-25 from 84th Avenue to US 36 will be closed with an additional lane closing at 11 p.m. All lanes and the ramp will reopen by 5:30 a.m. the following morning.
This bridge work is part of a project that constructs a 1400-foot long flyover ramp connecting southbound I-25 to eastbound I-270 and reconstructs southbound I-25 between 84th Avenue and I-76 in concrete. The new flyover is scheduled to open in November 2005. Sema Construction, Inc. of Littleton is the contractor of this $20.5 million project.
[Report this as objectionable content.]
SUBMIT COMMENT
Rate the above story
Talk Back :
submit comments to the story
*Note: you need to
log-in
to add a comment or rating.
Thank you! Your comment has been updated.
*A comment must be between 1 and 1000 characters.
*Please refrain from using explicit language.
CONTRIBUTOR INFORMATION
John Eisel
Denver
, COLORADO
John Eisel has posted
2865
stories and
12
comments since joining on
9/14/2005
. John Eisel's average story rating is
4.39
.
view profile »
view other postings from John Eisel »
SAVE AND SHARE THIS STORY
digg
Google
del.icio.us
Yahoo!
reddit
newsvine
What is this?
STORY RSS FEEDS
All stories
All stories in Northglenn
All stories by John Eisel
WANT TO WRITE FOR YOURHUB.COM?
Want to see the stories you write and the photos you shoot featured in the YourHub.com Thursday print section available
all over the Front Range
and with home subscriptions of the
Rocky Mountain News
and
The Denver Post?
All you have to do is
register
, then post a
story or column
,
start a blog
or
tell everyone
what events are happening in town. We will print the best stories, columns, event listings, photos and blog entries in our print sections.
ADVERTISEMENT
Loading Ad
Loading Ad
ADVERTISEMENT
Loading Ad