Ask Dot: When will 120th Ave construction start?
Contributed by: John Eisel on 3/21/2008

I have a question for Ask Dot.

When is Thornton going to step up and complete the widening of 120th Avenue between Holly Street and Quebec Street? They have been waiting for funding for at least five years. What's happening with this street improvement?

Russ Pierce
Brighton


Russ,

We asked David Nighswonger, director of public works for the city of Thornton, and he said the design is complete and the project will go out to bid next month. Construction is expected to start in August and last approximately 12 months. The city has budgeted about $3.6 million.

Nighswonger said the project will widen that stretch from one lane in each direction to two lanes in each direction, with a left turning lane in the middle. At no point will 120th Avenue be totally closed to traffic.

For further questions citizens are asked to contact Pete Brezall, project manager for city of Thornton, at 720-977-6251.

Do you have any questions to ask? Click here and we'll do our best to find out.



SUBMIT COMMENT

Rate the above story



Talk Back : submit comments to the story

*Note: you need to log-in to add a comment or rating.

CONTRIBUTOR INFORMATION

John Eisel

Denver , COLORADO

John Eisel has posted 2865 stories and 12 comments since joining on 9/14/2005. John Eisel's average story rating is 4.39.
SAVE AND SHARE THIS STORY
STORY RSS FEEDS
WANT TO WRITE FOR YOURHUB.COM?
Want to see the stories you write and the photos you shoot featured in the YourHub.com Thursday print section available all over the Front Range and with home subscriptions of the Rocky Mountain News and The Denver Post? All you have to do is register, then post a story or column, start a blog or tell everyone what events are happening in town. We will print the best stories, columns, event listings, photos and blog entries in our print sections.

ADVERTISEMENT
Loading Ad

Loading Ad
ADVERTISEMENT
Loading Ad